The work will be staged over several years. The first year (2018) will be for preparation, mobilization and advance work. A single segment of the bridge superstructure will be replaced in each of the subsequent five years. Within each segment, the bridge will be replaced on a half and half basis with single-lane, bi-directional traffic controlled by temporary traffic signals. Both traffic lanes will be open during seasonal shutdowns.
The work in 2024 will include the installation of expansion joints, final paving and the restoration of the site.
For more information or to be added to our contact list please contact us.